New Mitas plant in Otrokovice

Agro Napló
In the beginning of 2014 Mitas commenced production of tyres in the new plant in Otrokovice, Czech Republic at full capacity. Construction of the new production hall was completed on 31 May 2013 and on 2 July 2013, the first tyre was cured there. The total investment was about EUR 39.8 million, which includes construction, transfer and modernisation of the production technology. The new Mitas plant in Otrokovice now produces mostly Mitas branded tyres but also Cultor and Continental brands with a production capacity of 42,000 tonnes a year.

Photo by Mitas

 

“We managed to build this new plant, which is the most advanced of all Mitas production facilities, in under 12 months,” said Josef Křemeček, Otrokovice and Zlín plant director. “Mitas is committed to using the best available technology, and this makes the new plant one of the most advanced in the world in manufacturing agricultural radial rear tyres,“ added Josef Křemeček.


Photo by Mitas

Mitas managed to move all of the tyre production from its previous facility at the Continental Barum industrial park to the new location near the TOMA industrial park in less than a year. Mitas had to move all of its tyre production from the existing Otrokovice production hall, which it had rented for a limited time from Continental since 2004, when Mitas acquired the agricultural tyre division from Continental. The new plant in Otrokovice makes radial agricultural tyres.


Photo by Mitas

“Thanks to close cooperation and investments made in our other plants, we were able to optimise production capacity so the deliveries to our business partners during the process of transition were not affected,” said Jaroslav Čechura, Mitas' CEO.


Photo by Mitas

 

 

Key points on Otrokovice plant:

 

  • On 7 August 2012, the construction of the new production hall started.
  • The new hall was completed on 31 May 2013.
  • The total area of the new production plant is 24,000 m2. The plot is 78,000 m2.
  • First tyre in Otrokovice new plant was cured on 2 July 2013.
  • The new facility has a production capacity of 42,000 tons of tyres per year.
  • The total investment in the new Otrokovice plant is roughly CZK 1 billion (about EUR 39.8 million).

 


Photo by Mitas

 

Címlapkép: Getty Images
NEKED AJÁNLJUK
CÍMLAPRÓL AJÁNLJUK
KONFERENCIA
AgroFuture 2024
Új rendezvény a fenntarthatósági követelményeről és innovációs lehetőségekről!
AgroFood 2024
Országos jelentőségű rendezvény az élelmiszeripari vállalkozások számára!
Vállalati Energiamenedzsment 2024
Tudatos vállalati energiamenedzsment a hazai cégeknek!
Agrárium 2024
Jön a tavasz kiemelkedő agráripari konferenciája!